วันพุธที่ 28 กันยายน พ.ศ. 2554

Freedom Tower September 2010

The following information was last updated on October 1, 2010. Multiple cranes on site for steel and concrete installation Tower steel is now above floor 40 Concrete is now being installed above floors 33 and 34 Both the south and north cores are now being erected as the structure rises "Cocoon" safety system now in place around upper perimeter, to rise with structure Final concrete installation on the sub-grade structure, including the surrounding plaza Utility installation and tie-ins Crews are coordinating substructure construction while maintaining PATH service Special Thanks to: The Lower Manhattan Development Corporation www.wtc.com www.rebuldgroundzero.com The National September 11 Memorial and Museum and www.wtcprogress.com



http://www.youtube.com/watch?v=VGtv-Y3qq2o&hl=en

Thanks To : วิศวกรรม Buy Cheap Civil Construction Survey

วันเสาร์ที่ 30 กรกฎาคม พ.ศ. 2554

Freedom Tower February 2011

The following information was last updated on February 23, 2011. -Facade installation began mid-November; now above floor 27. -Tower steel is now above floor 56. -Concrete is now being installed above floor 48. -Spray-on fireproofing underway. -Multiple cranes on site for steel and concrete installation. -Both the south and north cores are now being erected as the structure rises. -"Cocoon" safety system now in place around upper perimeter, to rise with structure. -Utility installation and tie-ins. -Crews are coordinating substructure construction while maintaining PATH service. Special Thanks to: The Lower Manhattan Development Corporation www.wtc.com www.rebuldgroundzero.com The National September 11 Memorial and Museum The Port Authority of New York and New Jersey and www.wtcprogress.com



http://www.youtube.com/watch?v=IZzAAwKJqwA&hl=en

Recommend : Performance Laptops & Netbooks Moisturizing Gloves Deals Lcd Full Hd Power Soil Test 205GPSReceiverSportsWatch

วันอาทิตย์ที่ 22 พฤษภาคม พ.ศ. 2554

UPDATE! One World Trade Center / Freedom Tower Construction progress taken 3/18/2011 (Part 2)

I continue around to the Hudson River side and take another pan shot of The Statue of Liberty, Jersey City, and back to the Freedom Tower. I intended to add this final shot to the first video and leave for the day, but when I was almost back to the PATH station I noticed a glass panel and a corner piece was installed since I got there. So I waited to see if they would install more glass. After waiting about 5 minutes I see a glass panel being pulled out from the tower and workers slowly inch it over to it's corner to be installed. Before the second panel goes up on the corner more steel is being lifted to the top for installation. Again I think the workers where on a roll today and this is the most work I have seen done while stopping by the WTC site. After another 5 minutes workers pull another glass panel out from the tower and again begin to inch it into position to be installed. There was a lady also looking up at the workers moving the glass and didn't know what it was so I said that they were installing a piece of glass. So a few minutes later workers finish moving the second piece in place. Then waiting another 5 minutes workers pull out the last corner piece to put in place next to the glass panel for installation. This piece took the longest to install but they got it to work. After that corner of glass is installed I leave for the day back to New Jersey. Thumbs Up, Comment, and Subscribe!



http://www.youtube.com/watch?v=CJORPYSZXJE&hl=en

My Links : BestBuy Cheap Computer LED - LCD HDTV

วันจันทร์ที่ 28 มิถุนายน พ.ศ. 2553

1WTC Freedom Tower Update Feb-March 2010 A Tower Of Steel

On March 10 2010, The Base of the freedom tower has met its completion and now the office floors of the Freedom Tower are now beggining.. These floors are smaller than the mechanical floors so they will be built faster. The Memorial has been 96% complete with the south reflecting pool fully visible. Tower 4 has been working some progress and is expected to be finished in the borderline of 2010-2011.



http://www.youtube.com/watch?v=Ryao5fKpW70&hl=en